TE-Connectivity
Project overview
The project, implemented for a global leading client in industrial technologies, represents an innovative integrated energy solution. Over 1,900 panels, with a total power of 805 kWp, are distributed over three different configurations: A rooftop installation, a ground-mounted system in the land adjacent to the factory, and a system of carports that provide cover for the company parking lots and power the charging stations for electric cars and e-bikes. The plant, commissioned in June 2024, produces about 1,000 MWh of renewable energy per year.
Ground-mounted PV
installation
805 kWp
of installed capacity
Carport
with charging stations for electric cars and e-bikes
| Technical information | |
|---|---|
| Project Type | Ground-mounted PV installation + roof-mounted + PV carport |
| Location | Chieti |
| Commissioned | 2024 |
| Installed capacity | 805 kWp |